The elevator control cabinet is an electronic control device that installs various electronic devices and electrical components in a box-shaped structure with safety protection。It can also be called the elevator central control cabinet。下面
Hunan elevator projectHow to install the elevator control cabinet for the home, welcome to read!
First of all, let's look at what is the elevator control cabinet
The elevator control cabinet is a device used to control the operation of the elevator, which is generally placed in the elevator machine room, and the control cabinet of the elevator without the machine room is placed in the shaft or the shaft wall。The control cabinet is composed of sheet metal frame structure and bolt assembly。The sheet metal frame is uniform in size and can be easily hung and removed with plastic pins。The front panel is equipped with a rotating pin hook to form a lockable rotating door to access all components installed in the control cabinet from the front, so that the control cabinet can be installed close to the wall。
Hunan elevator projectHow to install the elevator control cabinet?
The installation of the control cabinet shall follow the principle of convenient maintenance and safe inspection, and shall be constructed in accordance with the position specified in the drawing。If the drawing is not specified, reasonable arrangements should be made according to the room area and installation form。To prevent water accumulation in the equipment room, install the control cabinet firmly on a cement pier with a height of 100 to 150mrn。When stabilizing the control cabinet, generally use bricks to cushion the control cabinet to the required height, and then lay the elevator pipe or elevator trough. After the elevator pipe or elevator trough is laid, then pour the cement pier to stabilize the control cabinet on the cement pier。
Elevator control cabinet installation precautions
(1) Keep a sufficient distance from the door and window, and the front distance between the door, window and the control cabinet should be no more than 1000mm。
(2) When the control cabinet is installed in rows and its width exceeds 5m, there should be access channels at both ends, and the width of the channel should not be less than 600mm。
(3) The installation distance between the control cabinet and the mechanical equipment in the machine room should not be 500mm。
(4) The verticality deviation of the control cabinet after installation should not be less than 3/1000。